Project NRTA-C-0149

Lakemont Station Area Pedestrian Safety Improvements

Crossing, sidewalk, and lighting improvements within a half mile of the Lakemont Transit Center, including the Lake Street and 4th Avenue intersection.

Current phase

  1. Planning (complete)
  2. Environmental (current phase)
  3. Design (not started)
  4. Procurement (not started)
  5. Construction (not started)
  6. Complete (not started)

The Regional Safety Action Plan identified the area around the Lakemont Transit Center as part of the region's High Injury Network. Seven pedestrian crashes, two of them fatal, occurred within a quarter mile of the transit center between 2020 and 2024.

Proposed improvements

  • Curb extensions and a leading pedestrian interval at Lake Street and 4th Avenue
  • A rectangular rapid flashing beacon crossing at Lake Street and Grove Street
  • 1.3 miles of new or widened sidewalk
  • Pedestrian-scale lighting on 4th Avenue

Project updates

  • Environmental review begins

    Staff have begun environmental documentation. A community walk audit with residents is planned for October 2026.

Timeline and milestones

  1. Grant award, complete

    2025

  2. Environmental review, in progress

    2026

  3. Design, upcoming

    2027

  4. Construction, upcoming

    2028

Funding

Funding sources for Lakemont Station Area Pedestrian Safety Improvements
SourceAmount
Safe Streets and Roads for All (SS4A)Federal$4,900,000
City of LakemontLocal$1,200,000
Regional Transportation Improvement FundLocal$700,000
Total project cost$6,800,000