Project NRTA-C-0127

Downtown Transit Signal Priority

Transit signal priority and signal equipment upgrades at 41 intersections in downtown Ridgeview to improve bus travel time and reliability.

Current phase

  1. Planning (complete)
  2. Environmental (complete)
  3. Design (complete)
  4. Procurement (current phase)
  5. Construction (not started)
  6. Complete (not started)

Buses in downtown Ridgeview spend an average of 18 percent of their running time stopped at traffic signals. Transit signal priority allows an approaching bus that is behind schedule to request a brief green extension or early green, without interrupting pedestrian crossing time.

Scope

  • Replacement of signal controllers and cabinets at 41 intersections
  • Installation of transit signal priority detection for Ridge Transit Routes 1, 6, 9, and 17
  • Accessible pedestrian signals with locator tones at all project intersections
  • Fiber communications linking signals to the City of Ridgeview Traffic Management Center

The Board awarded the construction contract to Meridian Signal Systems, Inc. on September 10, 2026. Notice to proceed is expected in November 2026, pending execution of the contract and submittal of bonds and insurance.

Project updates

  • Construction contract awarded

    The Board awarded IFB 26-004 to Meridian Signal Systems, Inc. for $6,842,300. Six bids were received.

Timeline and milestones

  1. Preferred alternative approved, complete

    December 2024

  2. 100 percent design, complete

    June 2026

  3. Construction contract awarded, complete

    September 2026

  4. Notice to proceed, in progress

    November 2026

  5. Construction and system testing, upcoming

    2027

Funding

Funding sources for Downtown Transit Signal Priority
SourceAmount
Congestion Mitigation and Air Quality Improvement Program (CMAQ)Federal$7,200,000
Ridge Transit Capital ReserveLocal$1,100,000
Regional Transportation Improvement FundLocal$1,100,000
Total project cost$9,400,000