IFB 26-012 · Invitation for BidsOpen
Accessible Bus Stop Modernization, Phase 2: Boarding Pads and Shelters
Construction of concrete boarding and alighting areas, curb ramps, sidewalk connections, and shelter foundations at 180 bus stops, and installation of 52 owner-furnished shelters.
Bids due Tuesday, October 20, 2026 at 2:00 p.m.
33 days remaining
Solicitation details
- Solicitation number
- IFB 26-012
- Type
- Invitation for Bids
- Status
- Open
- Funding
- Federally funded
- Estimated value
- Engineer's estimate: $2,800,000 to $3,200,000
- Contract term
- 300 calendar days from notice to proceed
- NAICS codes
- 238110 Poured Concrete Foundation and Structure Contractors
- 237310 Highway, Street, and Bridge Construction
- DBE goal
- 9 percent
- Related project
- Accessible Bus Stop Modernization
Key dates
| Event | Date and time |
|---|---|
| Issued | September 14, 2026(passed) |
| Pre-bid meeting (not mandatory)NRTA Board Room, 400 Commerce Street, Third Floor, Ridgeview | September 24, 2026, 10:00 a.m. |
| Written questions due | October 6, 2026, 5:00 p.m. |
| Bids due | October 20, 2026, 2:00 p.m. |
Scope summary
- Concrete boarding pads meeting ADA and PROWAG requirements at 180 stop locations
- Curb ramp reconstruction and sidewalk connections
- Shelter foundations and installation of 52 owner-furnished shelters
- Traffic control and maintenance of transit service during construction
Submission method and requirements
Electronic submittal through the NRTA Vendor Portal. Bids are opened publicly at 2:15 p.m. on the due date by Zoom.
- A bid bond of 5 percent of the total bid is required.
- Federal prevailing wage rates apply.
Solicitation documents
Addenda
No addenda have been issued. Check this page before submitting.