Project NRTA-C-0135
Regional Bicycle Network Expansion
Current phase
- Planning (complete)
- Environmental (complete)
- Design (current phase)
- Procurement (not started)
- Construction (not started)
- Complete (not started)
The Regional Active Transportation Plan identified gaps that prevent people from bicycling between communities. This program of projects fills the highest-priority gaps in three phases, beginning with segments that connect to schools and transit centers.
Phase 1 segments (in design)
- Millbrook Creek Trail extension, Station Avenue to Millbrook Community College (2.8 miles)
- Lake Street separated bike lanes, downtown Ridgeview to Lakemont (5.1 miles)
- Cedar Falls Rail Trail, Main Street to County Road 40 (4.4 miles)
Phase 2 route alternatives are being evaluated. A public survey on Phase 2 route preferences is open through October 16, 2026.
Project updates
Phase 2 route survey open
Residents can review Phase 2 route alternatives and share preferences through October 16, 2026.
Timeline and milestones
Existing conditions report, complete
September 2024
Segment prioritization approved, complete
May 2026
Phase 1 design, in progress
2026–2027
Phase 1 construction, upcoming
2028
Phases 2 and 3, upcoming
2029–2031
Funding
| Source | Type | Amount |
|---|---|---|
| Transportation Alternatives Set-Aside (TA)Federal | Federal | $8,400,000 |
| State Recreational Trails and Greenways ProgramState | State | $5,100,000 |
| Regional Transportation Improvement FundLocal | Local | $12,200,000 |
| Member jurisdiction contributionsLocal | Local | $6,000,000 |
| Total project cost | $31,700,000 |